After three years, long-planned rehabilitation projects are finally moving forward at Coupeville’s historic wharf.

Permits were granted to the Port of Coupeville to replace and repair degraded caps and piles that make up the wharf’s substructure at the end of year, three years to the date after port officials applied for them.

They Said It

Port Executive Director Chris Michalopoulos said the cap and pile project will cost around $1.4 million, with construction to be completed by fall or winter of this year.